Significant progress today. The demo guy came and got serious about removing plaster, from floor to ceiling. In come cases, there was drywall on top of plaster. The big thing that bothered me was the show stopper, that darn floor. It needed 1/2 inch sheet plywood (previous blog said 3/8). So, the project manager lent me his V8 Nissan and off I went for 7 sheets.
By this time, the demo guy was done with one wall and a fair way into that second wall. Around lunch time, we took some of the larger pieces and tossed in the back of the Nissan, he kept at it. A little after 1:30, the plaster removal was done, so it was now my turn - plywood time.
A few hours later, the plywood is down, but I did not nail it. Did not want to make any more noise, I need a break. That Sears circular saw has cut a lot of plywood and it continues to work fine. Significant progress, tomorrow the electrical inspector (I hope), then the new drywall goes up. Things do look better with new plywood down.