Kitchen Remodel, D-Day +32

This will be the last post until it's 100% complete. The finish carpenter, who by the way is very skilled, has been installing the crown molding, trim under the counter and installing the drawer and cabinet pull knobs. From this photo it's clear that the counter top, floor and lighting (to name a few) are not yet completed. Those are going in next week.

So next week is a big week. As mentioned above, the counter top and floor is planned for Tuesday, shortly after the electrical and plumbing will get finished off. Is it possible that this will be done on Friday? The project schedule indicated that December 7th / 8th would be the last day. Looks like a slide to the right, not too bad just a couple days is fine.

Some final painting needs to be taken care of over the weekend.